On-site coordination: keeping modular timelines honest

One timeline, clear dependencies
A single timeline should list dependencies: plaster levels before measure, paint before final hardware, flooring before skirting that meets wardrobes.
Factory and site
Factory releases should track site readiness — pushing production without confirmed dimensions creates rework. Buffer for monsoon and festival shutdowns in your city.
Photo logs
Weekly photo logs from site beat ad-hoc visits. They keep clients aligned and give the studio a clear audit trail when sequencing slips.